Belfast - Galway Route Accessibility Works
 

Galway Accessibility WorksName:  Belfast - Galway Route Accessibility Works - Package A
Locations:  Attymon, Woodlawn, Tullamore & Ballinasloe Stations
Client:  Iarnrod Eireann, Track & Signals HQ, Inchicore, Dublin 8.
Project Value:   € 3 million
Completion Date:  May 2009

Project Description:

This project was the first package in the upgrading of all Train Stations along the Belfast-Dublin and Dublin-Galway lines to provide improved accessibility to all station areas together with a number of station enhancements including the provision of CCTV, PA, fire and intruder alarms. Package A involved the upgrading of Tullamore, Ballinalsoe, Woodlawn and Attymon Stations.

The primary objective of this project was to render the four stations ( Attymon, Woodlawn, Tullamore & Ballinasloe) accessible to mobility and visually impaired customers in compliance with the relevant legislation and appropriate standards, guides and codes of practice.

The secondary objective was to carry out other enhancement works to the stations at the same time as the planned accessibility work in order to ensure that construction works are co-ordinated; cost efficiencies in design, tender and construction are achieved; abortive work is avoided and passenger disruption is minimised.  The enhancement works include the provision of CCTV, fire alarms, intruder alarms, expansion of telecom infrastructure and the installation of new signage.

Attymon Station works comprise:

  • Piling to underside of platform extension
  • Installation of L and Z-units
  • Installation of 100mm ducting and chambers
  • Installation of 150mm drainage pipe to soakaway
  • Installation of N100K Aco drain
  • Tarmacadam surfacing to platform and carpark and kerbing to carpark
  • Concrete post and timber infill fencing
  • Pallisade fencing around new equipment room
  • 1no. accessible parking bay and a set-down/pick-up bay adjacent to the station building.
  • Provision of new PA System, including speakers, cabling and interface with the Iarnrod Eireann Long Line System. 
  • Associated works include help points, listening points, induction loops and hearing enhancement, all at specified locations.
  • Provision of a CCTV system, covering help points and most areas of the platform, and including data storage capability.
  • Provision of lighting to the platform, car park and approach road.
  • The provision of emergency lighting.
  • Provision of a reinforced concrete slab for a new equipment room (supplied by Irish Rail).
  • Construction of a blockwork building adjacent to new equipement room to house further electrical equipment        

Woodlawn Station works comprise:

  • Installation of Z-units and 100mm coping units.
    Z units and copers were placed during night time possessions using a rail mounted 16t wheeled excavator. L units were unnecessary as there was an existing wall to the rear of the platform which could be utilized. In total,
  • Installation of 100mm ducting and chambers
  • Installation of 150mm drainage pipe to soakaway
  • Installation of N100K Aco drain
  • Tarmacadam surfacing to platform and carpark.
    This involved laying of approximately 150m2 of 110mm deep tarmacadam in two layers on the platform, the first layer being 14mm basecourse to a depth of 70mm and the second layer being 10mm wearing course to a depth of 40mm. There was also 100m2 of 40mm deep 10mm wearing course laid in the car park.
  • Line marking
    A 150mm white line approximately 90m long was sprayed on the platform edge and a 200mm yellow line of the same length on the rear of the new coping units. Irish rail standard lettering was sprayed on the new tarmacadam surface and thermo plastic line marking was used to mark the disabled parking bay and set down area.
  • Concrete post and timber infill fencing.
  • 1no. accessible parking bays and a set-down/pick-up bay.
  • New fully automatic sliding door to the entrance.
  • New automatic door actuators to internal doors.
  • New electric roller shutter to entrance.
  • Provision of new seating to the waiting room
  • Fully compliant accessible WC.
  • Provision of new PA System, including speakers, cabling, station control equipment, and interface with the Iarnrod Eireann Long Line System.  PA coverage to include platforms, car park adjacent to the station buildings, waiting room, toilet and other general public areas.  Associated works include 1no new help points, 2no induction loops and hearing enhancement, all at specified locations.
  • Provision of a CCTV system, covering help points, platforms, car park and most public areas of the station, and including data storage capability.
  • Provision of lighting to the platform and the area of the car park local to the accessible bay
  • The provision of emergency lighting.
  • Works to small power, to facilitate the above. 
  • Renovation of an existing room to form a new equipment room. This was confined to installation of a new MF ceiling (20m2 approx) and a steel security mesh above. The ceiling, walls and floor were then painted.

Ballinasloe Station works comprise:

  • A defined pedestrian route from the public boundary to the station building.
  • 2no. accessible parking bays and a set-down/pick-up bay adjacent to the station building.
  • A new entrance from the car park to the ticket hall.
  • Compliant steps and ramps to the new entrance and to the platform.
  • Automatic glazed bi-parting sliding doors to entrance door, platform door.
  • Reconfiguration of ticket hall and ticket office including demolition of internal walls and relocation of staff canteen facilities.
  • Provision of new dual level ticket window
  • Provision of matwells to external doors
  • Fully compliant accessible WC
  • Upgrade of WC cubicle to ambulant disabled standard.
  • Replacement of floor finishes
  • Redecoration of station interior
  • Provision of new PA System, including speakers, cabling, station control equipment, and interface with the Iarnrod Eireann Long Line System.  PA coverage to include platforms, car park adjacent to the station buildings, waiting room, booking offices, toilets, lifts and other general public areas.  Associated works include help points, listening points, induction loops and hearing enhancement, all at specified locations.
  • Provision of a CCTV system, covering help points and most public area of the station, and including data storage capability.
  • Upgrade to the station lighting to all public areas, and to the areas of the carpark local to the accessible bays.  The provision of emergency lighting.
  • Provision of mechanical services to the station buildings to suit changes to toilets and other facilities.
  • Works to small power, to facilitate the above.  Provision of builders work associated with the M&E services within the building.
  • Provision of a new equipment room.
    and steps.
  • Modification of the cement loop track and signalling including a 44m reduction in length of the down platform to facilitate installation of the new footbridge.              

Tullamore Station works comprise:

  • A defined pedestrian route from the public boundary to the station building.
  • 5no. accessible parking bays and a set-down/pick-up bay adjacent to the station building
  • Automatic glazed bi-parting sliding doors to entrance door, platform door.
  • Relocation of ticket validators
  • Provision of new dual level ticket window
  • Provision of matwells to external doors
  • Fully compliant accessible WC
  • Upgrade of 1no. WC cubicle to ambulant disabled standard in both male and female toilets
  • Replacement of floor finishes
  • Redecoration of station interior
  • Provision of new PA System, including speakers, cabling, station control equipment, and interface with the Iarnrod Eireann Long Line System.  PA coverage to include platforms, carp park adjacent to the station buildings, waiting room, booking offices, toilets, lifts and other general public areas.  Associated works include help points, listening points, induction loops and hearing enhancement, all at specified locations.
  • Provision of a CCTV system, covering help points and most public area of the station, and including data storage capability.
  • Upgrade to the station lighting to all public areas, and to the areas of the carpark local to the accessible bays.  The provision of emergency lighting.  Provision of mechanical services to the station buildings to suit changes to toilets and other facilities.
  • Works to small power, to facilitate the above.  Provision of builders work associated with the M&E services, including containment, buried ducts, access chambers etc.
  • Renovation of an existing room to form a new equipment room.
  • Resurfacing of all platforms, including the installation of new copers to gauge, and the provision of drainage.  The installation of foundations for station signage.
  • Construction of a new footbridge with lifts and steps.
  • Modification of the cement loop track and signalling including a 44m reduction in length of the down platform to facilitate installation of the new footbridge.              